CASE STUDIES

Data Center Hourly Supply with Wind Power

Dec 5, 2022

Project location

Sweden

EnergyTag audited

No

Temporal matching

1 hour

Geographical matching

Country level

Tracking method

Granular Certificates

Share

Project stage

  • Planning

  • Live demo

  • Commercial

Organisations

Temporal matching of wind and hydro supply for Microsoft data centers in Sweden via Vattenfall hourly matching platform.


Key takeaways:

1. Improves traceability of supply.

2. Advances Microsoft’s 100/100/0 goal.

3. Built scalable product platform used by other companies.


Next steps:

1. Scale product to other interested customers to develop hourly CFE supply/demand curves.

2. Support official issuance of hourly GOs.


Link

Project website: Link